The ninety-ninety rule of project scheduling *
The server upgrade at Client S has proceeded as follows:

  • Installing the new server -- a couple of hours.
  • Updating the new server -- a couple of hours.
  • Configuring the new server -- a couple of hours.
  • Moving almost all of the desktops out of the old domain and into the new one, and reconfiguring appropriately -- a couple of hours.
  • Moving the last two desktops out of the old domain and into the new one, and reconfiguring appropriately -- Two days so far, and counting. We pick up on Monday morning where we left off.


  • *The first ninety percent of a project takes the first ninety percent of the time; the last ten percent of a project takes the remaining ninety percent of the time.


    (Read 3 comments) - (Post a new comment)


    [info]maryread
    2009-06-13 07:59 pm UTC (link)
    This certainly explains a lot of what is going on here. For really rather wide values of "here".

    (Reply to this)